The Proposed Projects

Two 300 MW natural gas / diesel plants proposed for Marshdale and Salt Springs in Pictou County - 600 MW of fossil fuel generation, 20 km apart, paid for by Nova Scotia ratepayers.

Photo: GE LM6000 Hybrid EGT peaker system, SCE Norwalk. Wikimedia Commons, CC BY 4.0.

Both proposed sites in Pictou County, approximately 20 km apart on the same M&NE Pipeline lateral.

Overview

IESO Nova Scotia is procuring two "fast-acting natural gas power generation facilities" in Pictou County, each with a capacity of up to 300 MW. Both were registered for environmental assessment on December 22, 2025, and both received ministerial approval with conditions on February 19, 2026. Construction is scheduled to begin in 2027, with an expected operational life of at least 30 years.

Source
Marshdale EA Registration and Salt Springs EA Registration, Nova Scotia Environment, December 2025. Minister's Decision - Approval, February 19, 2026.

The proponent for both projects is IESO Nova Scotia, a provincial agency created in 2024 to manage electricity procurement. Unlike typical Canadian electricity procurements where private companies propose their own sites, IESO Nova Scotia pre-selected these sites, conducted preliminary studies, and is now running a competitive RFP for a third party to build and operate the plants.

Source
Draft Fast-Acting Generation RFP v1.0, IESO Nova Scotia, March 10, 2026. Available at ieso-ns.ca/procurement/.
2 × 300 MW
Combined 600 MW fossil fuel capacity
25+ years
Expected operational life per EARD
Class I
Standard, Less Rigorous Environmental assessment classification
Approved
Both approved with conditions, Feb 19, 2026

Marshdale

Marshdale site — PID 65245375, near Lorne, Hopewell, and Eureka. Project area: 55.95 ha.

The Marshdale facility is proposed for PID 65245375, near the communities of Lorne, Hopewell, and Eureka in the Municipality of Pictou County. The project would construct and operate a natural gas facility with combustion turbines and associated infrastructure including access roads, a substation, and buildings.

Source
Marshdale EA Registration page, Nova Scotia Environment. Marshdale EARD, Strum Consulting (prepared for IESO Nova Scotia), December 15, 2025.

The EARD describes a water injection system for emissions control requiring a peak extraction rate of 175 m³/hour, serviced by 14–19 production wells. The EARD's own groundwater modelling shows that 18–42% of pumping at Marshdale could come from depleting Cameron Brook, a local watercourse.

Source
Marshdale EARD, Section 3.3 (water supply) and Appendix (hydrogeological assessment), Strum Consulting, December 2025.

The environmental assessment received public comments (published in two parts) and was approved with conditions by the Minister on February 19, 2026.

Source
Minister's Decision (PDF), Conditions (PDF), Public Comments Part I (PDF), Part II (PDF).

Marshdale By the Numbers

6 turbines
~50 MW each, 300 MW total capacity
833 m
Nearest residence to project footprint
55.95 ha
Project area (12.55 ha footprint cleared)
325,594 t
CO²e per year when operating
CategoryDetailSource
Water — Peak Extraction175 m³/hr (175,000 L/hr)EARD Section 3.3.2.3
Water — Average Use23–31 m³/hr at 25% capacity factorEARD Section 3.3.2.3
Production Wells14–19 wells (up to 162 at peak demand)EARD Table 8.3
Stream Depletion18–42% of pumping from Cameron Brook depletionEARD Section 8.5.4.3
Wastewater Discharge50 m³/hr peak, discharged to surface waterEARD Section 3.3.2.3
Diesel Fuel Storage~9 million litres (5-day supply at full load)EARD Section 3.3.2.2
Diesel Consumption75,000 L/hr at full capacity; up to 20% of operating hoursEARD Section 3.3.2.2
Stack Height30 m, exhaust temperature 452°CEARD Table 3-5, Appendix B
Noise at Nearest Home40 dBA (nighttime limit: 40 dBA)EARD Table 7.18
Construction Jobs100–125 short-term; 10–15 permanentEARD Section 10.2
Wetlands Altered3 wetlands totalling 1.75 haEARD Section 6
Species at Risk DetectedCanada warbler (Threatened), Eastern wood-pewee (Special Concern), Atlantic salmon, American eelEARD Tables 10.15, Section 9
Source
All figures from Marshdale EARD, Strum Consulting, December 2025. Section and table references in table above.

The Minister’s Decision

On February 19, 2026, Minister Timothy Halman approved the Marshdale project. The decision letter contains a single substantive sentence:

“Following a review of the information provided by the Independent Energy System Operator (IESO) Nova Scotia, and all the comments received through the environmental assessment process, I am satisfied that any adverse effects or significant environmental effects of the undertaking can be adequately mitigated through compliance with the attached terms and conditions.”
Source
Minister’s Decision — Marshdale (PDF), February 19, 2026.

Conditions of Approval

The approval came with 8 categories of conditions — but read them carefully. These are not environmental limits. They are instructions to go do the actual environmental work: submit a design, write a wildlife plan, do the archaeology survey, form a committee. The substantive environmental questions — how much water can be withdrawn, what emissions are permitted, what noise levels are acceptable, how many hours the plant can operate — are not addressed. Those are deferred entirely to future Industrial Approval and Water Withdrawal Approval applications under Part V of the Environment Act, processes that have not yet begun.

ConditionRequirement
Project Design (4.1)Provide detailed final design and environmental mitigations before construction
Species at Risk (5.1–5.2)Submit species location data to DNR; submit Wildlife Management Plan to ECC, DNR, and ECCC
Archaeology (6.1–6.2)Stop work on any archaeological find; complete subsurface testing for elevated-potential areas
Wetlands (3.7)Obtain Wetland Alteration Approval before altering any wetlands
Community Liaison (7.1)Form and operate a CLC for the duration of the project
Mi’kmaq Engagement (8.1)Develop and implement a Mi’kmaq Communication Plan
Commencement (3.2–3.3)Begin work within 2 years; notify Department 30 days before starting
Annual Reporting (3.4)Submit concordance table on condition status by January 31 each year
The “assessment” approved a plan to do the assessment

The environmental assessment did not determine whether these plants can operate safely. It approved a plan to figure that out later. The conditions require IESO to submit a detailed design, a wildlife management plan, archaeological testing, and a Mi’kmaw communication plan — all after approval. The actual environmental limits on water, air, noise, and operations will be set in future Part V approval processes that have not yet begun. The Minister approved the project before the environmental work was done.

Source
Conditions of Approval — Marshdale (PDF), February 19, 2026.

What the Public Said

The Marshdale EA received 51 public and organizational submissions during the comment period (December 22, 2025 – February 9, 2026): 45 anonymous public comments and 6 organizations — Pictou Landing First Nation, Kwilmu’kw Maw-Klusuaqn (KMK), Sierra Club Canada Foundation, Ecology Action Centre, Canadian Association of Physicians for the Environment, and Margaree Environmental Association. Not a single submission supported the project.

KMK’s 6-page letter directly challenged the province’s claim that the project would not impact Mi’kmaq rights:

“Contrary to the statement in your previous letter that ‘the nature of this project is not likely to lead to appreciable adverse impacts to credibly asserted or established Mi’kmaq Aboriginal or Treaty rights,’ it is the understanding of the KMK that this project has significant potential to impact salmon, moose and black ash, at a minimum. Accordingly, it has the potential to cause appreciable adverse impacts to the Mi’kmaq’s established and asserted fishing, hunting and harvesting rights.” — Kwilmu’kw Maw-Klusuaqn (KMK), Director of Consultation
“Atlantic salmon are of great importance to the Mi’kmaq of Nova Scotia and are considered sacred to our culture and way of life. This species remains a foundational food source across Mi’kma’ki and would historically feed our people year-round. Loss of access to salmon threatens Mi’kmaq food security, self-determination, and rights-based harvesting practices.” — Kwilmu’kw Maw-Klusuaqn (KMK)
“With Pictou Landing being the nearest Mi’kmaw Community and having a dark history of large-scale industrial developments adjacent to their community, such as the Boat Harbor Project, it is imperative that the local Mi’kmaw Communities are adequately informed well in advance of large-scale projects such as this.” — Kwilmu’kw Maw-Klusuaqn (KMK)
“The Office of L’nu Affairs was in error when it failed to identify concerns or conduct an adequate assessment of impacts to rights. … KMK therefore emphasizes that a thorough, good faith consultation process must now be initiated both provincially and federally, consistent with the duty to consult.” — Kwilmu’kw Maw-Klusuaqn (KMK)
“Across multiple issue areas, the assessment exhibits a consistent and material pattern: potential adverse effects are systematically understated, not because evidence demonstrates they are insignificant, but because key analytical steps are deferred, scoped narrowly, or based on assumptions that are neither defined nor tested within the EA record itself.” — Sierra Club Canada Foundation
“We reviewed the Environmental Assessments for the proposed Marshdale and Salt Springs 300MW natural gas power generating facilities and find these assessments to be both inadequate and suspicious. They are inadequate because they fail to properly investigate non-fossil fuel alternatives, and suspicious because they do not establish the need for natural gas power development in the current Nova Scotia context.” — Margaree Environmental Association
“In the Pictou County region Mi’kmaq majority-owned, shovel-ready 150 MW/600–1,200 MWh BESS exists in Trenton. The EAC is concerned that the deployment of these gas plants will undermine this business case for the deployment of these BESS plants.” — Ecology Action Centre
“Groundwater withdrawal from nearby aquifers would reduce the natural cold-water inputs that sustain these refugia. … If this assemblage constitutes ‘low ecological significance,’ it raises serious questions about how ecological value is being defined.” — Anonymous commenter, Stellarton (self-identified marine ecologist)
“Summer 2025 produced a significant drought in our area. The East River flowing through Stellarton was so low that rocks were visible above the water — something I cannot recall seeing in my 39 years living here.” — Anonymous commenter, Stellarton area
“Spending roughly a billion dollars, committing us to burning fossil fuel for 20–30 or more years is fiscally irresponsible. There are cheaper and more environmentally appropriate alternatives.” — Anonymous commenter, Lower Three Fathom Harbour
Source
Public Comments Part I (PDF) and Part II (PDF), Nova Scotia Environment. KMK submission filed February 10, 2026 (6 pages).

Salt Springs

Salt Springs site — PIDs 00851287, 65049983, 00846311, 65177198, near Limerock and Six Mile Brook. Project area: 72.08 ha.

The Salt Springs facility is proposed across four properties (PIDs 00851287, 65049983, 00846311, 65177198), near the communities of Limerock, Six Mile Brook, and Central West River in the Municipality of Pictou County. Like Marshdale, it would construct and operate a 300 MW natural gas facility with combustion turbines and associated infrastructure.

Source
Salt Springs EA Registration page, Nova Scotia Environment. Salt Springs EARD, Strum Consulting (prepared for IESO Nova Scotia), December 15, 2025.

The Salt Springs site requires 9–12 production wells for water injection, with the same 175 m³/hour peak extraction rate as Marshdale. Both sites would also discharge approximately 50 m³/hour of treated wastewater to surface water.

Source
Salt Springs EARD, Section 3.3 (water supply), Strum Consulting, December 2025. Marshdale EARD, Section 3.3 (wastewater discharge rates).

The Salt Springs assessment received public comments (published in three parts) and was also approved with conditions on February 19, 2026.

Source
Minister's Decision (PDF), Conditions (PDF), Public Comments Part I (PDF), Part II (PDF), Part III (PDF).

Salt Springs By the Numbers

6 turbines
~50 MW each, 300 MW total capacity
706 m
Nearest residence to project footprint
72.08 ha
Project area (12.72 ha footprint cleared)
325,594 t
CO²e per year when operating
CategoryDetailSource
Water — Peak Extraction175 m³/hr (175,000 L/hr)EARD Section 3.3.2.3
Water — Average Use23–31 m³/hr at 25% capacity factorEARD Section 3.3.2.3
Production Wells9–12 wells (up to 65 at peak demand)EARD Table 8.3
Wastewater Discharge50 m³/hr peak, discharged to surface waterEARD Section 3.3.2.3
Diesel Fuel Storage~9 million litres (5-day supply at full load)EARD Section 3.3.2.2
Diesel Consumption75,000 L/hr at full capacity; up to 20% of operating hoursEARD Section 3.3.2.2
Stack Height30 m, exhaust temperature 452°CEARD Section 10.2
Noise at Nearest Home41 dBA unmitigated, 40 dBA mitigated (nighttime limit: 40 dBA)EARD Tables 7.18, 7.19
Construction Jobs100–125 short-term; 10–15 permanentEARD Section 10.2
Wetlands of Special Significance11 wetlands identified within project areaEARD Section 8
Black Ash Trees52 individual trees (29 occurrences) in project areaEARD Section 10
Species at Risk DetectedCanada warbler (Threatened), Eastern wood-pewee (Special Concern), wood turtle, mainland moose habitat nearbyEARD Sections 9, 10
Source
All figures from Salt Springs EARD, Strum Consulting, December 2025. Section and table references in table above.

The Minister’s Decision

The Salt Springs project was approved on the same day as Marshdale (February 19, 2026) with an identical decision letter containing the same single substantive sentence:

“Following a review of the information provided by the Independent Energy System Operator (IESO) Nova Scotia, and all the comments received through the environmental assessment process, I am satisfied that any adverse effects or significant environmental effects of the undertaking can be adequately mitigated through compliance with the attached terms and conditions.”
Source
Minister’s Decision — Salt Springs (PDF), February 19, 2026.

Conditions of Approval

The conditions are identical to Marshdale’s — same 8 categories, same language. Same pattern: instructions to do the environmental work after the approval, not before. No limits on water withdrawal, emissions, noise, or operational hours. All deferred to future Part V approvals.

Source
Conditions of Approval — Salt Springs (PDF), February 19, 2026.

What the Public Said

Salt Springs received 78 public and organizational submissions, published in three parts: 72 anonymous public comments and the same 6 organizations. As with Marshdale, not a single submission supported the project. Many commenters are local residents who raised concerns about their wells, the 2025 drought, and the rushed timeline:

“The project has been labeled as the most cost-effective path but to what end? … The environmental review report was released over the Christmas period with requests for commentary by February the 9th 2026. Everything seems to be rushed. The whole process to this point appears to be that the project is a done deal.” — Anonymous couple, Salt Springs
“We are very concerned about the proposed amount of water needed for this project which estimates usage to be equivalent to 750 homes per year. This is over 10 times the current draw in this area. … Should private wells go dry it appears that homeowners will be tasked to prove this project is the root of the problem. We have been here for 40+ years, raised a family and have never had an issue with our well, even with this past year of extreme drought.” — Anonymous couple, Salt Springs (40+ year residents)
“Approving a 300-megawatt industrial power generation facility in this location circumvents the zoning protections that rural residents relied upon when purchasing property and establishing homes. … If provincial approval processes can override municipal zoning restrictions to permit major industrial facilities in residential areas, then no rural community in Nova Scotia possesses meaningful protection against similar impositions.” — Anonymous commenter, within 1 km of site
“I live in Salt Springs, Nova Scotia. My grandmother and her grandmother washed their clothes in Six Mile Brook. Now, I am blessed to walk the same river with my granddaughter. … I really have no concerns, other than our Provincial Government thinks that they can fast track a fossil fuel burning energy plant within a stone throw from my family and neighbours. Really? I am very confused.” — Anonymous resident, Salt Springs
“The project proposes ongoing withdrawals of clean water for operational use at a time when local water systems have already demonstrated significant vulnerability. During the summer and early fall of 2025, severe drought conditions resulted in very low water levels in Six Mile Brook and the West River from June through October.” — Anonymous commenter, Gunn Road area
“Overbuilding of gas generation would be ineffective, inefficient, and environmentally damaging, and costly, especially when there are lower carbon alternatives. The dash to gas risks negative and unnecessary impacts on the environment and on ratepayers.” — Ecology Action Centre
Source
Public Comments Part I (PDF), Part II (PDF), and Part III (PDF), Nova Scotia Environment.

Combined Impact: Both Sites Together

Because these are two identical plants under a single procurement, the combined numbers are what Nova Scotia is actually signing up for.

651,188 t
Combined CO²e per year — 2.4% of NS emissions, per site
350,000 L/hr
Combined peak water extraction
18 million L
Combined diesel fuel storage on site
150,000 L/hr
Combined diesel consumption at full capacity
MetricMarshdaleSalt SpringsCombined
Capacity300 MW300 MW600 MW
Turbines6612
Project Area55.95 ha72.08 ha128.03 ha
Cleared Footprint12.55 ha12.72 ha25.27 ha
CO²e / Year325,594 t325,594 t651,188 t
Peak Water Extraction175 m³/hr175 m³/hr350 m³/hr
Production Wells14–199–1223–31
Wastewater Discharge50 m³/hr50 m³/hr100 m³/hr
Diesel Storage~9 million L~9 million L~18 million L
Nearest Residence833 m706 m
Construction Jobs100–125100–125200–250
Permanent Jobs10–1510–1520–30
Source
Combined figures calculated from Marshdale EARD and Salt Springs EARD, Strum Consulting, December 2025. Individual site figures from EARD sections referenced above.

Why Two Sites 20 km Apart?

No published justification exists

No analysis has been published explaining why two sites were chosen over one, or why both are located in Pictou County. The community has not been told why this decision was made.

If the justification is redundancy, the 20 km separation between Marshdale and Salt Springs does not deliver it. Both sites share the same vulnerabilities:

Two sites 20 km apart protect against a localized fire or equipment failure at one plant. They do not protect against the regional events - ice storms, pipeline disruptions, transmission failures - that actually threaten an isolated grid like Nova Scotia's.

Meanwhile, two sites mean the community hosts double the infrastructure and double the environmental footprint. The Maritimes & Northeast Pipeline runs through five counties. Existing generation sites like Trenton or Point Tupper would provide genuine geographic separation. The decision to concentrate both plants in Pictou County was made before any public process began.

Source
Analysis based on Marshdale and Salt Springs EARDs (site locations, pipeline connection details), December 2025; NS Power grid topology; Maritimes & Northeast Pipeline routing.

Technology

Generation: Gas Turbines or Reciprocating Engines

The EARDs describe the plants as using "combustion turbines," but the RFP's Functional Specifications leave the door open for either aeroderivative gas turbines (such as the GE LM6000) or reciprocating internal combustion engines (RICE), such as those manufactured by Wärtsilä. The final technology choice will be made by the winning bidder.

Source
Marshdale EARD and Salt Springs EARD, Section 2 (Project Description), December 2025. RFP Functional Specifications (Exhibit T), Hatch Engineering, Rev. 2, February 2026.

Emissions Control: Water Injection

The EARDs describe water injection as the method for controlling nitrogen oxide (NOx) emissions. Water is injected into the combustion chamber to lower flame temperatures, reducing NOx formation. This is the oldest method of emissions control for gas turbines, dating to the 1970s.

Water injection drives the massive water demand: 175 m³/hour peak extraction per site, dozens of production wells, and ongoing wastewater discharge. However, the EARDs themselves acknowledge that "alternative Project technology with less water demand" exists.

Alternatives exist

Two commercial alternatives eliminate nearly all water demand. Dry Low Emissions (DLE) combustion turbines achieve equal or better NOx performance through combustion chamber design, with near-zero water consumption. Reciprocating engines use closed-loop radiator cooling and need less than 5 litres of water per hour. The RFP does not require water injection - the 175 m³/hour figure reflects a design choice in the EARD, not a requirement of the procurement.

Source
Marshdale EARD, Section 3.3, December 2025. GE Vernova, Water Injection for NOx Reduction; GE Vernova, Dry Low NOx (DLN 2.6) Combustion Upgrade; Wärtsilä, "Combustion engine vs. Aeroderivative gas turbine: Water consumption".

Primary Role: Synchronous Condensers

Despite being described as power plants, these facilities would generate electricity less than 25% of the time. More than 70% of the time, they would operate as synchronous condensers - the turbine or engine is shut down and disconnected, but the generator keeps spinning, connected to the grid.

A synchronous condenser provides physical grid stability: resistance to frequency changes, the ability to ride through short circuits, and voltage support. These services become critical as coal plants retire and wind and solar - which do not inherently provide them - increase. These are primarily grid stability machines that occasionally generate electricity, not power plants in the traditional sense.

Source
RFP Functional Specifications (Exhibit T), Hatch Engineering, Rev. 2, February 2026: generation <25% of time, synchronous condenser mode >70% of time. Available via the RFP Analysis page.

Timeline and Process

The speed of this procurement has a specific cause, and it is not the 2030 coal phaseout. NS Power was originally developing the first 300 MW itself, targeting 2027. The plan was to build in two stages. In Fall 2024, the Department of Natural Resources transferred the procurement to the newly created IESO Nova Scotia, resetting the clock. The target is now 2029–2030, and all 600 MW must be built at the same time.

Source
NS Power, IRP Action Plan Update 2025. IESO Nova Scotia Draft RFP v1.0, March 2026, Section 1 (Background).

The Clean Electricity Regulations Deadline

The real driver of the timeline is the federal Clean Electricity Regulations. A new gas plant emits 460–550 tonnes of CO2 per gigawatt-hour but faces an emissions limit of 65 t/GWh. It cannot operate under that limit. However, plants that qualify as "planned units" are exempt until the end of 2049.

To qualify, four milestones had to be met by December 31, 2025:

The EARDs were filed on December 15, 2025 - sixteen days before the deadline. This likely explains why IESO Nova Scotia pre-selected the sites rather than letting bidders propose their own. Three of the four milestones are publicly verifiable. The fourth - the $10 million equipment contract - has no public trace.

Source
Clean Electricity Regulations (SOR/2024-263), Section 3. Marshdale and Salt Springs EARDs, filing date December 15, 2025.

Key Dates

Date Event
Fall 2024 Procurement transferred from NS Power to IESO Nova Scotia
December 15, 2025 EARDs filed for both Marshdale and Salt Springs
December 22, 2025 Both projects registered for environmental assessment
December 31, 2025 Federal "planned unit" qualification deadline
February 19, 2026 Both projects approved with conditions
March 10, 2026 Draft RFP released
2027 Scheduled construction start
2029–2030 Target operational date
Source
Dates compiled from: Marshdale and Salt Springs EA Registration pages; IESO NS Draft RFP v1.0, March 2026; Clean Electricity Regulations (SOR/2024-263).